|
Cable demands were loaded into the stores area as complete kits and the kits picked and bagged in readiness for loading to the shop.
Each kit could contain up to 70 cable assemblies.
At each stage in the process the kits were completed prior to moving through to the next manufacture stages.
This approach resulted in high levels of work in progress and long lead-times through the system.
In addition the work area was cluttered with unnecessary items contained in the area including excess kit bins and cable reels, tooling cabinets and racks.
|
|
The team evaluated the existing process and identified the value adding and waste elements using flowcharting, string diagrams and process activity charting techniques.
This analysis provided the necessary information to develop a revised floor layout which would minimise the people and material movement within the process, enable co-location of personnel, improve process connectivity and support the introduction of single piece flow manufacture within the section.
Without significantly interrupting manufacture the team dismantled and relocated 42 workstations, re-organised and significantly reduced the cable stock holding, relocated tooling and improved access using shadow boards and implemented visual control.
In addition, sufficient space was freed up within the target area to allow the creation of a dedicated training bay with space for 12 workstations.
Back to case studies
|
|
The process now operates a pull system from the production operatives.
They complete a single cable assembly and move the job onto the inspection rack adjacent to their work area.
They then withdraw the 'next job' from their line side rack and continue assembly.
The withdrawn job is a visual trigger to the cable cutting team to pull from their preceding process and cut the required cable for the next assembly.
Demand in turn moves upstream to the stores area where the next components are picked for the next scheduled assembly, loaded into a 'bin' with the necessary documentation and placed into the cable cutting Kanban.
Electric cable supplies
Process Improvement (Manufacturing)
|